Skip to main content

Maltsovsky Portland begins commissioning works

Published by , Editor
World Cement,


On 17 November 2015, Maltsovsky Portland began commissioning works on a modern automated module line for the shipment of bulk cement trucks.

Commissioning works are due to be completed within two weeks. They will be performed under the supervision of equipment supplier IBAU Hamburg.

At first no-load tests will be conducted on pieces of equipment such as blowers aeration systems, metering valves, bucket elevators, shakers, bag filters, etc.

The work on the modernisation of the cement separation loading module is completed. Its second phase - a site loading bulk cement railcars - should be completed by the beginning of the construction season in 2016.


Edited from source by Joseph Green. Source: Eurocement

Read the article online at: https://www.worldcement.com/europe-cis/25112015/maltsovsky-portland-begins-commissioning-works-68/

You might also like

 
 

Embed article link: (copy the HTML code below):