In November 2016, Gebr. Pfeiffer SE received an order to supply a vertical roller mill that will be set up in HeidelbergCement's new 3000 tpd kiln line at its Kaspi plant.

The type MPS 4000 B mill is equipped with an SLS 3750 B classifier and has been designed for a capacity of 270 tph raw meal. The mill will be delivered with an enlarged housing to allow raw material with up to 10% moisture to be dried almost exclusively with the available preheater gases.

The order was placed through the Chinese General Contractor Sinoma Chengdu.

Commissioning of the plant is scheduled for 2018.

Read the article online at: https://www.worldcement.com/asia-pacific-rim/10012017/gebr-pfeiffer-to-provide-mill-to-kaspi-plant-in-georgia/

You might also like

Optimisation 2019

Optimisation 2019

Optimisation 2019 is an online conference for professionals in the cement sector. Since this is a completely virtual conference, you can join us from anywhere in the world, absolutely free. Register for free today »

 

Solar plant online for Bharathi Cement

Bharathi Cement has recently commissioned a 10 MW ground-mounted solar power plant at its manufacturing facility in Kadapa, Andhra Pradesh.

 
 

Embed article link: (copy the HTML code below):