Fives installs raw meal grinding plant at QNCC

Published by
World Cement,


French engineering group, Fives, has installed the raw meal grinding plant at Qatar National Cement Co.’s (QNCC) new cement production line. The installation was carried out ton 29 March 2017.

The raw meal grinding plant includes a 6.6 MW FCB-B mill. The raw mill shell weighs 198 t and its 17.2 m long and 6.4 m in diameter. The shell was moved and erected using a self-propelled modular transport.

The erection of the raw meal grinding plant follows the commissioning of two FCB B mills for cement grinding in January and February. The new production line will have a capacity of 5000 tpd.

Read the article online at: https://www.worldcement.com/africa-middle-east/27042017/fives-install-raw-meal-grinding-plant-at-qncc/

You might also like

Sustainability 2020

Sustainability 2020

An online conference focusing on sustainability in the cement industry. Join us for presentations covering topics such as: Alternative fuels, air pollution control, dust control, carbon capture and more. Register for free today »

 
 
 

Embed article link: (copy the HTML code below):