Bamburi Cement finishes construction of production line at Nairobi grinding plant

Published by , Editor
World Cement,


Construction works of Bamburi Cement’s new KES.4 billion production line at its Nairobi grinding plant are now complete with commissioning expected in the last quarter of the year.

This marks increased cement production for the company, with the new line injecting additional production capacity of 900 000 tpy to increase total capacity at the plant to 2.4 million tpy. Overall, the annual combined total capacity of Bamburi Cement’s two plants (Nairobi and Mombasa) will increase to 3.2 million tpy.

Additionally, the new development will see Bamburi Cement start production of two high strength cement brands, namely Power Plus and Power Max, that were previously only produced at the company’s Mombasa Plant. The Nairobi plant was only producing Tembo and Nguvu brands.

“The contractor is on schedule and will soon be handing the project over to the company for full operation. Further, we are happy that the line has produced the first bag of cement three days ahead of the scheduled time. The next phase is to conduct tests on the system for efficiency and thereafter commission it,” said the company’s CEO, Seddiq Hassani.

This is the first phase of the company’s capacity expansion programme which commenced three years ago with the actual construction starting in 1Q17.

Hassani added: “Bamburi Cement appreciates the continued government’s support to the manufacturing sector’s growth and development. As a company, we are keen to support the Government’s Big Four Agenda in which the sector is expected to contribute 15% of the Gross Domestic (GDP) by 2022.”

The key components of the new production line that are already completed include the 140 tph Vertical Cement Grinding Mill (VCM) complete with grid recirculation, process dedusting and hot gas generator, two new cement storage silos with a capacity of 1500 t each, new 120 tph cement packing machine, power installation among other auxiliary equipment.

Bamburi Cement capacity increase comes hot on the heels of projected demand in both domestic and regional markets attributed to the investment in the construction sector mainly in the individual home builder segment and in major infrastructural activities. According to the Economic Survey report released in April 2018, the overall expenditure on roads is expected to increase from KES.173.7 billion in 2016/17 to KES.198.4 billion in 2017/18, attributed to increased development expenditure on roads which is expected to grow by 19.2%.

Further, the company’s capacity expansion programme is expected to support the Government’s Affordable Housing agenda to deliver 500 000 housing units by 2022 by ensuring the country’s projected demand for cement is met.

Read the article online at: https://www.worldcement.com/africa-middle-east/03072018/bamburi-cement-finishes-construction-of-production-line-at-nairobi-grinding-plant/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Cement news 2018