Construction continues at Tula plant

Published by
World Cement,


Construction is continuing at the Tula cement plant’s new production line with commissioning of the FCB Horomill for raw meal grinding and the FCB Kiln. This following the commissioning of the first and second FCB Horomills for cement grinding in December 2016 and January 2017, respectively.

Fives were awarded the contract to design, supply, erect, and commission a new complete 3300 tpd production line at the Tula plant in May 2015. The project features a pyroprocessing line including an FCB Kiln, FCB Zero-NOx Preca, FCB Preheater and Pillard NovaFlam. Cement and raw meal grinding will be done using FCB Horomills and associated FCB TSV classifiers, while a FCB B-mill with TSV classifier will be installed for petcoke grinding.

Fives delivered the first 1500 tpd production line at the Tula plant in 2006. First clinker was produced at the plant in December 2007, with first cement following in January 2006.

Read the article online at: https://www.worldcement.com/the-americas/27062017/construction-continues-at-tula-plant/

You might also like

 KHD

KHD Technical Webinar Series

Over the coming weeks, World Cement will be hosting a series of technical webinar presentations from KHD! Each presentation will be led by industry experts and provide a detailed discussion of KHD’s product offerings to the cement industry.

Find out more and register for the series »

 

Martin Marietta increases quarterly cash dividend

The company has announced that its Board of Directors approved a 4% increase in its quarterly cash dividend, raising it from US$0.55 per share to US$0.57 per share on the company’s outstanding common stock.

 
 

Embed article link: (copy the HTML code below):