Construction continues at Tula plant

Published by
World Cement,


Construction is continuing at the Tula cement plant’s new production line with commissioning of the FCB Horomill for raw meal grinding and the FCB Kiln. This following the commissioning of the first and second FCB Horomills for cement grinding in December 2016 and January 2017, respectively.

Fives were awarded the contract to design, supply, erect, and commission a new complete 3300 tpd production line at the Tula plant in May 2015. The project features a pyroprocessing line including an FCB Kiln, FCB Zero-NOx Preca, FCB Preheater and Pillard NovaFlam. Cement and raw meal grinding will be done using FCB Horomills and associated FCB TSV classifiers, while a FCB B-mill with TSV classifier will be installed for petcoke grinding.

Fives delivered the first 1500 tpd production line at the Tula plant in 2006. First clinker was produced at the plant in December 2007, with first cement following in January 2006.

Read the article online at: https://www.worldcement.com/the-americas/27062017/construction-continues-at-tula-plant/

You might also like

 WCT2020

Optimisation 2020

Optimisation 2020 provides a unique online forum for cement industry professionals to hear first-hand from experts through a series of exclusive presentations from cement producers and industry experts.

Find out more and register for the series »

 

 Spotlight

World Cement Spotlight with Rockwell Automation

World Cement Editor, David Bizley, sat down with Michael Tay, Advanced Analytics Product Manager at Rockwell Automation to discuss his recent article in World Cement.

Entitled ‘Smooth Sailing’, this article explains how machine learning can help save energy, reduce downtime and predict equipment failures, thus enabling the smooth running of cement plant operations.

Watch the interview now »

 
 
 

Embed article link: (copy the HTML code below):