Skip to main content

Raw meal grinding performance tests in Barroso plant

Published by , Editor
World Cement,


Having started up the No. 2 kiln in Barroso plant and after inaugurating the new line installed for Holcim Brasil SA, Fives has satisfactorily carried out performance tests on the FCB Horomill® 4400 grinding plant, implemented to produce 420 tph of raw mix.

These 20-hours performance tests enabled Lafarge-Holcim to produce 438 tph of raw mix with a product fineness of 11% rejects at 90 µm, and an electrical power consumption limited to 10.8 kWh/t for the whole grinding plant.

This FCB Horomill® grinding plant allows for reaching product moisture of 0.05%.

Performance tests on the kiln line will be carried out soon.

Read the article online at: https://www.worldcement.com/the-americas/18102016/raw-meal-grinding-performance-tests-in-barroso-plant/

You might also like

World Cement podcast

The World Cement Podcast

In this special joint episode of the World Cement Podcast, and Cementing Europe’s future, the podcast of CEMBUREAU, David Bizley and Koen Coppenholle take a deep dive into the Clean Industrial Deal and a discussion of what it means for the European cement industry.

Listen for free today at www.worldcement.com/podcasts or subscribe and review on your favourite podcast app.

Apple Podcasts  Spotify Podcasts  YouTube

 

Filter Bags For The Future

César Javier Alanis Cruz, W. L. Gore & Associates, presents a case study from Cementos y Concretos Nacionales, highlighting how the plant enhanced production and extended filter life by optimising its coal mill baghouse filtration system.

 
 

Embed article link: (copy the HTML code below):