Having started up the No. 2 kiln in Barroso plant and after inaugurating the new line installed for Holcim Brasil SA, Fives has satisfactorily carried out performance tests on the FCB Horomill® 4400 grinding plant, implemented to produce 420 tph of raw mix.

These 20-hours performance tests enabled Lafarge-Holcim to produce 438 tph of raw mix with a product fineness of 11% rejects at 90 µm, and an electrical power consumption limited to 10.8 kWh/t for the whole grinding plant.

This FCB Horomill® grinding plant allows for reaching product moisture of 0.05%.

Performance tests on the kiln line will be carried out soon.

Read the article online at: https://www.worldcement.com/the-americas/18102016/raw-meal-grinding-performance-tests-in-barroso-plant/

You might also like

World Cement podcast

World Cement Podcast

In the latest episode of the World Cement Podcast, Senior Editor David Bizley is joined by Dr Andrew Minson of the GCCA to discuss the ins and outs of the recently launched Low Carbon Ratings (LCR) system.

Listen for free today »

 
 
 

Embed article link: (copy the HTML code below):