Estanda supply Improvest diaphragm
Published by Joseph Green,
Editor
World Cement,
Estanda has carried out the supply and the commissioning of an ‘Improvest’ diaphragm to the Eagle Cement plant in The Philippines.
The former middle diaphragm showed material flow problems in the diaphragm plates, seizing problems and downtimes, as well as subsequent wearing of these plates.

The project consisted of a complete substitution of the previous liners for an Improvest diaphragm with acement flow set to regulate an increase in mill production. In addition, the steel plate installation with wear-resistant materials was undertaken in this project in a CM-2 cement mill, with a diameter of 4.2m in April 2015.
The aim of this project was to supply all steel parts as well as the middle diaphragm assembly and the setting up of the grinding installation.
Edited from source by Joseph Green. Source: Estanda
Read the article online at: https://www.worldcement.com/asia-pacific-rim/18092015/estanda-supply-improvest-diaphragm-619/
You might also like
The World Cement Podcast - The changing face of cement in Europe
In this special joint episode of the World Cement Podcast and Cementing Europe’s Future, Senior Editor David Bizley is once again joined by Koen Coppelholle, CEO of Cement Europe (formerly CEMBUREAU). The two discuss the reasons behind the rebrand, a new action plan for cement, and the future of the industry.
Tune in to the World Cement Podcast on your favourite podcast app today.

