Eagle Cement plans third line at Bulacan plant

Published by
World Cement,


Philippine cement maker, Eagle Cement Corp., (ECC) eying construction of a third production line at its Bulacan plant. According to local media reports, the proposed line would come online by 2018.

The Bulacan plant currently has capacity of 5.2 million tpy. The new line would add 2 million tpy to that, bringing total capacity to 7.1 million tpy. The plant only began operations in 2010 and has already added a second to keep up with an increase in demand.

“The construction of the third line is already fully funded,” the company told reporters on a recent plant tour.

The company also said it was looking to construct a smaller plant in Cebu by 4Q17 with a capacity of 2 million tpy. Funds for the project will be provided by an initial public offering of 11.5% of the company’s shares, planned for early May. The IPO aims to raise PHP9.2 billion (US$183.3 million).

Read the article online at: https://www.worldcement.com/asia-pacific-rim/07042017/eagle-cement-plans-third-line-at-bulacan-plant/

You might also like

 

 WCT2021

WCT2021

At WCT2021 you will hear from a range of industry leaders and technical experts as they discuss the key challenges facing the cement industry and the latest solutions on offer. Register for free today »

 

Getting the measure of things

Felix Bartknecht, Ferdinand Kaschewski, and Sriparthan Sriraman, SICK, consider the best solutions for monitoring the status and health of kiln inlet process gas analysis systems in order to achieve the highest plant availability and product quality.

 
 

Embed article link: (copy the HTML code below):