- Heidelberg Materials UK is supplying the concrete for the main works at Sizewell C in East Suffolk.
- The concrete is being used to construct the initial phase of the cut-off wall which will create a watertight barrier around the main construction area for the new nuclear power station.
- Heidelberg Materials will supply around 35 000 cubic metres of concrete over the next seven months from both static and mobile plant.
Heidelberg Materials UK has secured the contract to supply the concrete for the main works at Sizewell C on the East Suffolk coast.
The material is being used to construct the initial phase of the cut-off wall, which will run around the perimeter of the site of the new nuclear power station. The structure, which is comprised of concrete panels and a plastic wall, will extend more than 50 metres into the ground. It will create a watertight barrier to enable around four million cubic metres of earth to be excavated from the site to allow construction of the two reactor units.
Around 35 000 cubic metres of concrete will be supplied over the next seven months, initially from Heidelberg Materials’ Ipswich concrete plant. Heidelberg Materials UK is also installing a mobile batching plant at the Sizewell C site, which is expected to be operational by the end of the year. The concrete contains admixtures from Sika to ensure workability, allow a longer window for placing and compaction and inhibit the ingress of groundwater.
“Our nuclear team has wide-ranging experience in the sector and is sharing best practice and lessons learned from our close involvement in supplying Hinkley Point C over the last decade,” said Sean Hunter, Head of Nuclear Operations at Heidelberg Materials UK.
“Throughout the past 12 months we have supported the Sizewell C team, in collaboration with our supply partners, to develop and trial the concrete mix, supporting the project’s objective to deliver Sizewell under intelligent replication of Hinkley.”