Loesche has announced that Tianjin Cement Industry Design & Research Institute Co. Ltd. has ordered two LM 53.3+3 CS Loesche mills for grinding clinker.
For the PT Semen Baturaja cement plant, the customer Tianjin Cement Industry Design & Research Institute Co., Ltd. has placed an order for two type LM 53.3+3 CS Loesche mills for clinker grinding. Both of the mills have been designed with a capacity of 175 t/h and material is ground to a fineness of 3400 Blaine. Every mill is fitted with a gearbox with a power of 4200 kW.
The lead time for the main components of the mill is 9 months and the gearboxes are supplied within 12 months. The commissioning of both vertical roller mills is planned for the end of next year.
The order follows a previous delivery, in 2012, of the LM 46.2+2 CS Loesche mill, which is still in operation.
In 2013, Loesche GmbH established the subsidiary company PT Loesche Indonesia with an office in Jakarta.