Sinoma reports that the 6000 tpd Sephaku Cement clinker line was successfully ignited and put into production. The project is contracted to Sinoma Nanjing. A ceremony was held to mark the occasion, attended by representatives of the employer and the contractor.

This South African project has been given great importance by Sinoma, which has dealt with problems such as delayed drawing approval, late equipment arrival and strict local regulations to ensure the smooth running of the project. The targets of ignition and production were successfully realised on 15 August.

The project is still ongoing and Sinoma is now focused on the next stage and the completion of commissioning.


Adapted from press release by

 

Sub-Saharan Selection: Introductory Overview

In this abridged article from World Cement’s September 2014 issue, Paul Maxwell-Cook explores some of the markets in Sub-Saharan Africa that are gaining significant cement industry attention.

Dangote Cement reaches out to distributors

Having successfully completed ignition and production testing on Obajana line 4, Dangote Cement is reportedly set on streamlining the distribution process.